CASE STUDIES
Hybrid power on real Australian worksite

CASE STUDY FPS20-10
YANKALLIA
FPS20-10 + fast deploy 10kW array & 21kWh Battery
Future Power Systems delivered a reliable hybrid power solution for a remote South Australia Water worksite. The systems power lunchrooms, offices and a toilet block over an 8 month period.
96.1%
renewable power
3,759 kWh
total power consumed
9,418.58L*
fuel saved
$20,720.88*
fuel cost savings
.*The figures marked with stars represent estimates or calculations of fuel savings and cost reductions.
CASE STUDY FPS20-10
SWOOP AREO - MURCHISON TEST FACILITY
FPS20-10 + fast deploy 10kW array + 14kWh Battery
Swoop Aero’s Murchison Test Facility uses the FPS20-10 with a 10kW solar array and 14kWh battery to power a remote drone testing site, including chargers, communications, office/lunchroom facilities, and water and septic pumps. The site operated 10 hours a day, Monday to Friday over a 2 year period.
88%
renewable power
7,597 kWh
total power consumed
25,098.7L*
fuel saved
$55,217.14*
fuel cost savings
.*The figures marked with stars represent estimates or calculations of fuel savings and cost reductions.