CASE STUDY

Fulham

Reliable hybrid power in
challenging irradiance conditions

Gippsland

Victoria

1 Nov 2025 -

10 Jul 2026

FPS20-10

Deployed

The FPS20-10 hybrid power system delivered reliable, cost-effective power for temporary site facilities in a low-irradiance location, significantly reducing diesel use, operating costs, and emissions. 

PROJECT SNAPSHOT

Project Name

Fulham

Location

Gippsland, Victoria

Product Deployed

FPS20-10

Deployment Period

Project Name

Prpject Duration

Project Name

Diesel Generator Comparison

35kVA

WHAT WAS POWERED

THE CHALLENGE

The FPS Mini-25 is designed for sites that need more portable output than the Mini-15 or Mini-20, while still keeping the benefits of a trailer-mounted hybrid system.

​

It combines deployable solar generation, integrated battery storage and backup generation to support reliable temporary power across smaller worksites, remote applications and mobile site operations.

​​Higher-load temporary worksites

  • Remote equipment and site operations

  • Site amenities, lighting and communications

  • Temporary construction support

  • Mobile off-grid power applications

  • Projects needing increased portable hybrid capacity

DIESEL GENERATOR COMPARISON

The table shows the estimated diesel use and costs if a 35kVA generator was required to operate 24 hours a day for the duration of the project.

By using the FPS20-10 hybrid system insed of a 24-hour deisl genertor, the project acheived significant savings and emission reduction.

Parameter

Value

Project Duration

251 days

Operating Hours Based on 24-Hour-Use

6,024 hours

Estimated 24-0Hour Generator Fuel Use

2.1 L / hour

Diesel Price Used

$2.20 / L

Diesel Use with 24-Hour Generator Operation

12,650.4 L

Estimated Diel Cost Avoided

$27,830.88

Estimated Emission Reduction

34.16 tonnes CO2

PROJECT OUTCOME

THE FPS2-10 hybrid power system delivered reliable power throughout the 251-day deployment, even in challenging low-irradiance conditions.

Compared to a 24-hour diesel generator setup, the project achieved an estimated: 

52303215-4255-415e-9dd4-437c0fe2b8ef_edi

12,650.4 L

diesel use avoided

52303215-4255-415e-9dd4-437c0fe2b8ef_edi

$27,830.88

in diesel cost avoided

52303215-4255-415e-9dd4-437c0fe2b8ef_edi

34.16

tonnes of CO2 avioded

Related Products

3947A933-7EEA-4012-A534-5028E871AAE7 3.JPG

Planning temporary
or off-grid power?

Reduce generator runtime, fuel use and site servicing with an Australian-made hybrid power system.​ Built for construction, infrastructure, and remote sites.

Australian-made hybrid power systems that reduce fuel use, lower emissions, and keep projects moving.

Smarter power. Built for Australia. 

HYBRID SYSTEMS

FPS Mini-15

FPS Mini-20

FPS Mini-25

FPS20-10

FPS20-20

FPS20-60

Compare Systems

APPLICATIONS

Construction & Civil

Infrastructure

Remote Operations

Agriculture

Events

Mining

RESOURCES

Case Studies

Cost & Fuel

Hybrid Power Basics

Learning Centre

Technical Guidence

FAQs

GET IN TOUCH

1300 208 010

Australian made

Serving all of Australia

Based in Echuca

Request a Quote

IMG_1228.JPG

 

Future Power Systems acknowledges the Traditional Custodians of the lands and waters across Australia and recognises their enduring connection to Country, community, and culture. Based on Yorta Yorta Country, we are committed to working responsibly, learning continuously, and contributing to a future grounded in respect, reconciliation, and care for Country. 

Copyright © 2026 Future Power Systems - All Rights Reserved.

bottom of page