Powering Remote Operations Around the Clock

Updated: 3 days ago


CASE STUDY – FPS20-10 GEN 12

GOULBURN VALLEY, VICTORIA     |    1 JANUARY 2023 – 25 MAY 2025



Future Power Systems deployed the FPS20-10 Gen 1 hybrid power system to support a remote drone testing centre in the Goulburn Valley, Victoria.


The site had a unique operating profile, with high overnight battery-charging loads required for drone testing.

PROJECT SNAPSHOT

Project Name

Kite Aero Drone Testing Facility

Location

Goulburn Valley, Victoria

Product Deployed

FPS20-10

Application

Drone testing centre

Deployment Period

1 January 2023 - 25 May 2025

Project Duration

875 Days

Site Condition

High overnight battery charging load

Diesel Generator Comparison

30kVA diesel generator


WHAT WAS POWERED


The FPS20-10 supported temporary site facilities including:


  • 1 x 9m x 3m Office

  • Security and lighting systems

  • Septic and associated pumping systems

  • Data and communications systems


THE CHALLENGE


The site required consistent power for remote drone testing operations. This included overnight battery charging, lighting, security, data systems and communications infrastructure.


Unlike a standard temporary site facility, this deployment had high overnight charging demand, requiring the system to support critical loads outside typical daylight solar generation hours.



THE FPS SOLUTION


Future Power Systems deployed the FPS20-10 Gen 1, a containerised hybrid power system combining solar generation, battery storage and backup generation.


The system was designed to support daytime site loads while storing energy to meet overnight demand, with backup generation available as needed to maintain reliable power.


System configuration included:

  • Containerised hybrid power system

  • Integrated solar generation

  • Battery energy storage

  • Backup diesel generation

  • Remote site power capability

  • Support for overnight battery charging loads

PERFORMANCE OUTCOME


The Swoop Aero deployment demonstrated how hybrid power can support specialist remote operations with high overnight energy demand.


Across the deployment, the system generated 6.7 MWh of solar and used 0.9 MWh of backup generation.


By using the FPS20-10 Gen 1 instead of relying on a 24-hour diesel-only generator setup, the project achieved an estimated:



43,729.88L


of fuel saved

$96,205.73


in fuel cost savings

118.07


tonnes of CO₂ emissions avoided


SYSTEM USED: FPS20-10


The FPS20-10 Gen 1 is a containerised hybrid power system designed for construction, infrastructure, remote operations and temporary off-grid site applications.


It combines solar generation, battery storage, and backup generation to provide practical on-site power while helping to reduce diesel reliance.


Specification

FPS20-10

Format

Containerised hybrid system

Solar

Integrated solar generation

Battery

Up to 50kWh

Backup

Diesel generation

Best Suited For

Construction compounds, site amenities and temporary off-grid power

Many temporary sites still rely on diesel generators running for long periods, even when demand is low. This increases fuel use, operating costs, noise, maintenance and emissions.


Hybrid power systems provide a more efficient alternative by using solar and battery storage where possible, while retaining backup generation for reliability.

For sites like Kite Aero's Drone Testing Site, this means practical temporary power with lower diesel reliance and measurable environmental benefits.



NEED A SIMILAR SYSTEM FOR YOUR SITE?


Tell us about your site location, load requirements and project duration. Future Power Systems can recommend the most suitable hybrid power system for hire, purchase or configured deployment.




Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
bottom of page